Mumbai Trans Harbour Link races to catch deadline, 96.60% complete


Mumbai, Sep 22 (IANS): The prestigious Mumbai Trans Harbour Link (MTHL) is racing towards completion with 96.60% progress achieved, four months after the bridge superstructure was completed in end-May, officials said here on Friday.

Mumbai Metropolitan Region Development Authority (MMRDA) Commissioner Sanjay Mukherjee carried out a comprehensive inspection of the current status of the mega-project along with other senior officials as the MTHL rushed to meet the tentative November opening deadline announced earlier.

The 22-km, India’s longest sea bridge will connect Mumbai Navi Mumbai on the mainland and drastically travel time to various points in the state.

The project includes a total of 1,212 lighting poles of which 20 percent are already in place, said Dr. Mukherjee.

These lighting poles are equipped with a Central Control & Monitoring System and are specifically designed to withstand the challenges of being situated in the deep sea.

The poles are suitable for a saline environment, with a corrosion-free polyurethane coat, galvanization to prevent rush and prolong lifespan, structural design to withstand high winds, uniform illumination all across the sea link and shall come with a Lightning Protection System to safeguard against possible lightning strikes.

The MTHL was executed in three packages for civil works and a fourth package focussing on the Intelligent Transport System, an Automated Toll Collection System and electrical works.

In a pioneering application in India, the bridge itself utilizes Orthotropic Steel Deck (OSD) spans, ranging from 65m to 180m in length, and serves as a testament to the use of unique products and state-of-the-art construction methods, said Dr. Mukherjee.

Once operational, the MTHL will provide faster connectivity to the upcoming Navi Mumbai International Airport, the JNPA Port, Mumbai-Pune Expressway, Mumbai-Goa Highway and other locations, contributing to the growth and development of the region.

 

  

Top Stories


Leave a Comment

Title: Mumbai Trans Harbour Link races to catch deadline, 96.60% complete



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.