Ensure Bypass on Stills by October: HC


By Marcellus D’Souza

Apr 29: The High Court of Bombay at Goa presided over by Justice M S Sonak and Justice R N Laddha asked the Goa government to ensure the balance stretch of western bypass is completed within the stipulated time frame in October 2022.

The Division Bench observed that the work is “unduly delayed” and that works should complete within the time period as prescribed by the government itself, while it heard miscellaneous civil application (MCA) seeking to revise/modify the scope of the work in relation to the 2.75 kms stretch by including an elevated construction (stilts) for the portion of 0.98 kms.

“Accordingly, we see no difficulty in allowing this application. However, we are quite concerned about the works being completed expeditiously. As it is, this project has been unduly delayed. In terms of the work order issued to the contractors, the work on this balance stretch of 2.75 kms is to be completed by October 2022. The State should now ensure that this timeline is adhered to and observed by its contractor as far as possible,” the order states.

“Therefore, if the modification is to be permitted, the State government should also require the contractor to complete the work within the schedule prescribed, if necessary, by employing an additional workforce and machinery so that the project is not delayed again. Furthermore, suppose the existing contractor expresses the usual difficulties in completing the work. In that case, the government should seriously consider whether the contractor should be replaced so that the project is not once again delayed,” the court said disposing off the MCA.

The High Court, in Public Interest Litigation (Suo Motu), made several orders from time to time monitoring the progress of completion of the western bypass project to decongest the traffic through the town of Margao. The work to the extent of 8.75 kms is already complete, and this portion is presently operational. However, the work of approximately 2.75 kms is still pending.

The NGT, by order dated June 22, 2021 constituted a 10-member joint committee to look into this issue and come up with some solutions.

The order was however made without notice to the State of Goa. After notice, the State of Goa pointed out to the NGT about the pendency of the Public Interest Litigation (Suo Motu). Therefore, the NGT made an order dated November 10, 2021 deferring the proceedings before it. However, the Counsel for the State of Goa was requested to appraise this Court about the pendency of the Original Application before the NGT.

The 10-member committee recommended one of the alternatives involving a modified approach with a 0.98 km elevated structure which will lead to an increase in the cost of the project from the present estimated cost of Rs 148.41 crore to 218.94 crore approximately, but this will avoid filling of the water body and part diversion of the river.

The Court allowed for the western bypass on stilts on a stretch spanning 980 meters, making it abundantly clear that the State Government should require the contractor to complete the work within the schedule prescribed, if necessary, by employing additional workforce and machinery so that the project is not delayed again.

The High Court said, that in the event the existing contractor expresses the usual difficulties in completing the work, the Government should seriously consider whether the contractor should be replaced so that the project is not delayed once again. “We see no difficulty in allowing the Application. However, we are quite concerned about the works being completed expeditiously. As it is, this project has been unduly delayed. In terms of the work order issued to the contractors, the work on this balance stretch of 2.75 km is to be completed by October 2022. The State should now ensure that this timeline is adhered to and observed by its contractor as far as possible”, the High Court observed.

Granting the application, the High Court said the Advocate General has submitted that even the State authorities feel that the revision/modification as recommended by the Committee will be in the public interest and the environment interest. The Advocate General had said submitted to the Court that even an in principle approval has been accorded subject to directions from this Court. He pointed out that the Union Minister for Road Transport and Highways, during his visit to the State in January 2022, had announced that the Ministry would bear the entire cost of the western bypass. Accordingly, a formal proposal has been moved for funds.

Benaulim villagers have upped the ante for construction of the western bypass on stilts as they made an application containing as many as 1128 signature to the Benaulim panchayat to call a special gram sabha to discuss the issue.

A villager Roque Fernandes informed that the application containing the 1128 names and signatures has been entered in the village panchayat, with a plea to demanding a special gram sabha to discuss the western bypass issue.

He hoped the panchayat would accede to the demands of the villagers by convening the special gram sabha and facilitate a discussion on the contentious issue.
Farmers from Benaulim as well as the villagers have been waging a long drawn struggle over the last half a decade, demanding construction of the bypass on stilts, fearing that a bypass built on earthen embankments will devastate the flood plains of river Sal and destroy tracts of agricultural land and the biodiversity of the village.

The villagers had last month called on the South Goa MP Francisco Sardinha as well as TMC Rajya Sabha MP Luizinho Faleiro to take up the western bypass issue in Parliament given that the project is a central-government funded project.

  

Top Stories


Leave a Comment

Title: Ensure Bypass on Stills by October: HC



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.