Mangaluru: Decks cleared for concreting, widening of second phase of Shiradi ghat road


Daijiworld Media Network - Mangaluru (SP)

Mangaluru, Oct 11: The court has cleared the decks for the development of second phase concreting of Shiradi Ghat stretch of national highway 75. The work was pending after the company to which this contract was granted, defaulted and then went to court against cancellation of contract granted to it. Therefore, there has been a delay of about two years.

The second phase of this stretch had been granted to M/s G V R Infra Projects after tender was floated, in 2015. Although the company was expected to stock raw materials in advance and begin work immediately after the rainy season, it was observed that it failed to do so. Thereafter, department of highways had cancelled the tender, against which the company had approached the court. As a result, re-tendering process got delayed. As the court has upheld the decision of the highways department, the re-tendering process is in final stages now, it is gathered. With this, the people hope, the wretched stretches of this road will begin to provide pleasant experience to vehicle users soon.


Shiradi ghat road - file photo


National highways section of public works department has begun preparations to undertake this work now. In all probability, the work might begin in about a month from now. In the second phase, 12.38 km of concrete road (tender amount Rs 63.10 crore) and 21 km of asphalting work (tender amount Rs 22.18 crore) with a total outlay of Rs 85.28 crore will be undertaken. Ocean Construction will be undertaking this work.

The people using this road will have to take alternative routes to reach Hassan and Bengaluru. The district administration is expected to prescribe alternative routes for heavy vehicles, buses, and light vehicles during the period this work will be in progress.

  

Top Stories

Comment on this article

  • Flavian, Mangalore/Kuwait

    Wed, Oct 11 2017

    Let us dig a tunnel to reach PAK where missiles are stored.

    DisAgree [4] Agree [6] Reply Report Abuse

  • Flavian, Mangalore/Kuwait

    Wed, Oct 11 2017

    Pumpwell circle over bridge, Nantoor junction over bridge and Padil under pass etc. still under completion.
    May be they are waiting BJP to come to power !

    DisAgree [3] Agree [16] Reply Report Abuse

  • Marle, Kudla

    Sat, Oct 14 2017

    For the inauguration..

    DisAgree [1] Agree Reply Report Abuse

  • Mathew, Mangaluru

    Mon, Oct 23 2017

    It doesn't matter which ever govt comes. Its the same story and NH roads are monitored by central GOVT.

    Mangalore - Bangalore 4-lane Highway Project was implemented in 2005 and since then all Central and State Political Parties involved in this project have just sat on it.

    Roads between Hassan - Bangalore are good. Rest has been ignored till date.

    Mr Nitin Gadkari the current Minister of Road Transport Highways & Shipping please we are citizens who can't afford an Helicopter ride like you. But its because of we Taxpayers that your Helicopters are working.

    DisAgree [1] Agree Reply Report Abuse

  • R.Bhandarkar, Mangaluru

    Wed, Oct 11 2017

    This Ghat is proof of 'Ghatiya' leaders we have...

    DisAgree [13] Agree [17] Reply Report Abuse

  • Samantha Lewis, Mangalore/Dubai

    Wed, Oct 11 2017

    I am hearing this since my childhood decades passed still no any concrete solution. What happened to the plan they were about to give the project to a Japanese company for make a tunnel of high quality. No news, Oh sorry Japanese company will not serve cookies to the authorities.

    DisAgree [1] Agree [20] Reply Report Abuse

  • Jossey Saldanha, Mumbai

    Wed, Oct 11 2017

    We want Bullet Train from Mangaluru to Bangaluru ...

    DisAgree [3] Agree [27] Reply Report Abuse

  • R.Bhandarkar, Mangaluru

    Wed, Oct 11 2017

    Tumche 'Mumbai Bullet' Kaalen Zaallen?
    Tusssss gee?

    DisAgree [2] Agree [18] Reply Report Abuse

  • KRPrabhu, Mangalore /Bangalore

    Wed, Oct 11 2017

    Decks cleared for thickening pockets of the contractor....😀

    DisAgree [3] Agree [31] Reply Report Abuse

  • Vaishak, Namma KUDLA !!!!

    Wed, Oct 11 2017

    what happened to the proposed 6 lane tunnel highway in shiradi ghat ?

    DisAgree Agree [30] Reply Report Abuse

  • Aubb, Kuwait

    Wed, Oct 11 2017

    Oscaranna only can reply to you, hopefully!!!

    DisAgree [3] Agree [22] Reply Report Abuse


Leave a Comment

Title: Mangaluru: Decks cleared for concreting, widening of second phase of Shiradi ghat road



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.