17% of total 756 projects delayed by more than 5 years


New Delhi, Dec 18 (IANS): As many as 132 out of the 756 delayed projects or 17.4 per cent projects are running behind schedule by five years and more.

Delay in land acquisition and forest clearances, lack of infrastructure support and linkages, delay in tie-up for project financing and lack of infrastructure support and linkages are some of the other reasons for these projects running behind schedule.

Out of the 756 delayed projects, 144 have overall delays in the range of one to 12 months, 117 have been delayed for 13 to 24 months, 363 projects for 25-60 months and 132 projects have been delayed for 61 months and above.

Apart from this, as many as 364 infrastructure projects, each worth Rs 150 crore and above, have been hit by cost overruns of more than Rs 4.52 lakh crore, according to official data of the ministry of statistics and programme implementation, released for the month of November 2022.

It further stated that out of 1,476 projects, 364 reported cost overruns and as many as 756 projects were delayed.

 

  

Top Stories


Leave a Comment

Title: 17% of total 756 projects delayed by more than 5 years



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.