Puttur: Shiradi Ghat concreting work in progress, to open in June


Daijiworld Media Network - Puttur (MS)

Puttur, Mar 31: The concreting work of the 13 kilometre stretch of road between Kempuhole to Addahole in Shiradi Ghat is being done with greater speed and is expected to be complete by the end of May 2018. In all likelihood, the road will be open for traffic in the month of June.

Rs 74 crore has been released for this project and the work is being done by Ocean Construction India Private Limited company using latest machinery and modern technology imported from Germany.

Out of the 77 drains in this stretch, the work of 74 is complete. In addition, widening of three minor bridges is also in progress.

Ultra modern German machine for work

In order to complete the work faster and also for a more permanent solution for the road issues in Shiradi Ghat, Censor Paver machine from Germany was imported at a cost of Rs 10 crores. Every day two to three kilometres of road is being concreted with a thickness of 600 mm. Already 3 kilometre stretch of road on both left and right side has been completed. Rest 9 kilometres is in the first layer of granular sub-base (GSB) application and 3 kilometres stretch is in the second layer of dry lean concrete (DLC) application process. This information is given by Suresh Kumar, engineer of the company, who is at the site of work.

Unique technology for road construction

Shiradi Ghat receives heavy rains for nearly six months in a year. The mud of this ghat is very soft due to the continuous stream of water that flows in between the rocks. Because of this, it is very difficult to construct a firm and long lasting road in this ghat. Keeping this drawback in mind, a new and latest technology is being implemented in constructing permanent and long lasting road this time.

In order to prevent the mixing of mud with concrete, geotextile is applied before the start of concreting work. Cross filter drainage system is being built at distance of every 25 meters to avoid the continuous stream of water. Hard soil is being put in low lying areas of the ghat. This information was given by Raghavan, superintendent engineer of national highway authority.


Quality of work appreciated by the public

Ocean Construction Company, which is doing the present work of concreting, had done the first phase concreting of 11.77 kilometre stretch of the ghat between Heggadde and Kempuhole. The quality of work of the first phase done by this company was appreciated by people representatives, public and highway authority.

Now in order for the work to progress quickly, vehicular traffic has been closed on the ghat from January 12 this year.

"The deadline given by the government ends in August. However, we have taken all the measures to complete the project as soon as possible. The road will be open for vehicular movement by the end of May or beginning of June" said Sharfuddin, director of Ocean construction India Private Limited.

Shiradi Ghat road - a long-standing issue

Plying through Shiradi Ghat was a bottleneck for drivers as well as passengers for a long time. It was really an adventure to Maranahalli in Sakleshpur through the narrow bitumen road which passes between the ghat. It used to take three hours for this journey. During rainy season huge potholes were created on this road due to the moisture in the mud.

However, this time around a permanent concrete road is being built, which will enable two vehicles to pass at a time. The surface of the road is being made rough for the drivers to have grip and control while negotiating through this road. More than four bends are straightened already to avoid blind spots while driving.

National highway authority used to spend crores of rupees every year for asphaltization of the ghat as the road used to get damaged during the rainy season. However, this time around all are hoping the solution opted is a permanent one.

  

Top Stories

Comment on this article

  • Shaf Bhakt, Mangalore

    Sat, Mar 31 2018

    Please some one upload new video of the road in Shiradi Ghat.
    Dying to see how it looks!

    DisAgree Agree [12] Reply Report Abuse

  • Joseph F. Gonsalves, Bannur, Puttur / Mangalore

    Sat, Mar 31 2018

    During the tenure of Kumaraswamy and Yeddyurappa shiradi Ghat work was malicious and both Yeddy and Kumaraswamy have pocketed the money from the ill-works of the Shiradi road.

    NOW IT IS THE DEVELOPMENTAL WORKS OF CONGRESS UNDER THE CHIEF MINISTER HONORABLE SIDDHARAMAIAH TO KARNATAKA, SHIRADI GHAT WORK IS IN FULL SWING.

    VOTE CONGRESS FOR DEVELOPMENTS AND HUMANS WELFARE.

    UNDER CONGRESS RULE:

    NO CHURCH ATTACKS.
    NO HOME STAY ATTACKS.
    AT WHATSOEVER NO PUB ATTACKS.
    IN THE ASSEMBLY NO PORN WATCHERS.
    THROW OUT AMIT SHAH MAKING DIVIDING HINDUS.

    JAI KARNATAKA AND JAI INDIA

    DisAgree [29] Agree [59] Reply Report Abuse

  • Indian, Mlore

    Sat, Mar 31 2018

    This is National Highway my dear.... nothing to do with Sidhha.... Whn congress was at Centre were they sleeping to get this road rectified ??

    DisAgree [22] Agree [29] Reply Report Abuse

  • Joseph, India

    Sun, Apr 01 2018

    READ THE LAST PARA..when Congress was ruling they had no vision like how to fix the issue because it was a reason to swindle money..but these thinking of putting concrete came after BJP came to power...so vote for right party..

    DisAgree [7] Agree [2] Reply Report Abuse

  • Jossey Saldanha, Mumbai

    Sat, Mar 31 2018

    Siddaramaiah will keep his Promise ...

    DisAgree [33] Agree [54] Reply Report Abuse

  • Desi Jawan, Mangalore

    Sat, Mar 31 2018

    This is national highway. This is the progress of NaMo.

    DisAgree [50] Agree [44] Reply Report Abuse

  • Paul, Mangalore

    Sat, Mar 31 2018

    Yes it is N highway....but what did your Namo guys do when they were ruling Karnataka...your so called namo guys Yeddi. Gowda & shettiyar ..3 CM ' loaded with cortuption.....
    It's MR. Lobo ....who had pressurized...& taken innitative......rest all are taking credit....

    DisAgree [20] Agree [37] Reply Report Abuse

  • Abhijit, M'lore

    Sat, Mar 31 2018

    When BJP was in power in K'taka, useless & corrupt UPA was in power in center. NH comes under center not under state. So please don't come up with such questions.

    DisAgree [17] Agree [23] Report Abuse

  • PEDDA GUNDA, MANGALURU

    Sat, Mar 31 2018

    This is a classic example of our politician and bureaucrat planning & work efficiency . Shridi Ghat is in news from several decades for its road repairing. We got best of best engineers in our country and human resources along with natural resources but still struggling !!!!

    Any politicians out there to explain poor tax payer ? why deliberately happening and we dont have any other option to give a permanent solution ?

    DisAgree Agree [30] Reply Report Abuse


Leave a Comment

Title: Puttur: Shiradi Ghat concreting work in progress, to open in June



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.