Mangaluru: HC stay on removal of Miyawaki forest at Nanthoor – Flyover work stalled


Daijiworld Media Network – Mangaluru (MS)

Mangaluru, Nov 18: The construction of the overpass at Nanthoor junction in the city was progressing at a good pace. However, the entire process has been stalled due to a stay order issued by the high court (HC) preventing the removal of the Miyawaki forest.

The National Highways Authority of India (NHAI) had planned to commence work in October and had started clearing trees and leveling the hill on three sides. However, on October 9, the HC issued a notice to NHAI, instructing them not to remove the Miyawaki forest until further orders.

Vana Charitable Trust of the city established the Miyawaki forest with sponsorship from Singin International and Biocon Foundation. These companies filed a writ petition in the HC opposing the removal of the Miyawaki forest.

Although the Nanthoor flyover project was initially planned in 2001, it was canceled as the houses of Scheduled Castes (SCs) and an underground cable network were not removed. The Mangaluru City Corporation (MCC) granted permission to grow the Miyawaki forest in 2021, and it was inaugurated on June 5, 2022, on Environment Day. The forest now includes over 1,000 plants.

While the initial plan involved the removal of the Miyawaki forest, the responsibility was handed over to the local corporator. Ninety-nine trees near the junction were cut down after obtaining permission from the forest department. The ground near the apartment adjacent to the junction has been leveled, leaving a two-meter space. The MCC initially demanded Rs 2.5 crore to relocate the drinking water pipeline, but this amount was reduced to Rs 70 lac, and the pipeline will be shifted.

A demand of Rs 4.5 crore was made to remove Mescom electricity poles and cables, which was later agreed to be done for Rs 60 lac after extensive discussions. The telephone exchange company has agreed to remove their cables independently as they were laid without prior permission.

The statue of Srinivasa Mallya, located opposite Bhagawan Babbuswamy Daivastana, will need to be relocated. Additionally, the compound wall of the SC students' hostel needs to be demolished and rebuilt. The demolition of a commercial complex is also pending. NHAI officials have stated that they will only commence flyover construction after the service road is completed.

Abdulla Javed Azmi, project director of NHAI, said, “The work on the Nanthoor Junction overpass was supposed to begin in October after acquiring 90% of the land. Currently, 83% is available. The HC stay on the removal of the Miyawaki forest, which was grown with MCC's permission, has slowed down the project. We plan to present the ground-level situation to the court. Once the stay is lifted, the project will be completed within 24 months.”

 

 

  

Top Stories

Comment on this article

  • A Dsouza, Kulshekar

    Tue, Nov 19 2024

    When will these so called environmentalist see sense...Dont they and their families also drive on these crowded roads everyday? Let the development happen, it is in the best interest of all for generations to come... Trees can be planted again and they will grow... Cant stop progressing in the name of environment... Yes there is a threat, but let's finish the roads then plant as many trees, no problem

    DisAgree [1] Agree [7] Reply Report Abuse

  • Monty Dotor, Mangalore

    Tue, Nov 19 2024

    Instead of flyover make an underpass, Baat Khatam...

    DisAgree [16] Agree [7] Reply Report Abuse

  • Anil Shetty, Mangalore

    Tue, Nov 19 2024

    Vehicles stalled there in traffic and emitting CO has more harmful effects that easily outweigh the benefits of any Miyawaki forest there.

    DisAgree [2] Agree [33] Reply Report Abuse

  • Haneef, Mangalore

    Mon, Nov 18 2024

    Environmentalists not concerned when people die on these junctions because of bad road conditions but they bother trees which can be planted elsewhere too.

    DisAgree [6] Agree [30] Reply Report Abuse

  • Ajay, Mangalore

    Mon, Nov 18 2024

    If the forest was inaugurated in 2021, I am sure that the forests are no more than gardens. So relocate them. Also why do you have to remove a first just to raise pillars and girders for flyovers? This country will never improve. Mangalore contributes a lot to the state, however the roads are one of the worst.

    DisAgree [3] Agree [42] Reply Report Abuse

  • Ananda Moorthi., Thokkottu,575017.

    Mon, Nov 18 2024

    So many youngster's are dyeing in Road Accdents at Nanthoor side due to Traffic overcrowd.Flyover is the only Remedy.But......

    DisAgree [4] Agree [30] Reply Report Abuse

  • Ashok, Mangalore

    Mon, Nov 18 2024

    For me it’s totally waste of money . Problem started after making island. Originally there’s no island straight road. Very simple make wider road and put signal Here somebody wants to make money . Why in Mangalore signals working all over the world signals working day and night

    DisAgree [10] Agree [13] Reply Report Abuse

  • JD, Mangaluru

    Mon, Nov 18 2024

    This is so sad to hear. We understand the importance of trees, environment etc, however these kind of important projects should be not delayed by environmentalists. Trees should be relocated elsewhere. Nanthoor junction has faced some many problems till now and so many lives are lost due to accidents etc. Its important this project progresses and gets completed on time.

    DisAgree [3] Agree [43] Reply Report Abuse

  • Sense_shetty, Kudla

    Mon, Nov 18 2024

    They allowed the diversion of a major river and the destruction of thousands of trees for the Netravati river diversion project. Yet, when it comes to road development—critical for preventing accidents and easing the daily struggles of thousands of commuters—the High Court blocks progress. It raises questions about their priorities. Is the government influencing the judiciary to stall such projects? Or is there a personal stake, perhaps ancestral land, involved? A practical solution like directing NHAI to transplant trees or ensure compensatory afforestation could address environmental concerns while facilitating essential development

    DisAgree [2] Agree [48] Reply Report Abuse


Leave a Comment

Title: Mangaluru: HC stay on removal of Miyawaki forest at Nanthoor – Flyover work stalled



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.