Rio Olympic Park hits 97 percent completion


Rio De Janeiro, Jan 27 (IANS): Construction work at Rio de Janeiro's Barra Olympic Park, the main venue cluster for this year's Olympic Games, has hit 97 percent completion, organisers said.

The complex, which will will host 16 of the 42 Olympic sports and nine of the 23 Paralympic disciplines, was 95 percent finished in December, Xinhua news agency reported.

Meanwhile the velodrome, which will host the track cycling test event from April 29 to May 1, is 80 percent ready, up from 76 percent in December.

At Deodoro Park, the second largest venue cluster, Youth Arena has made the fastest progress, reaching 80 percent completion compared with 75 percent in December.

The venue will host basketball, fencing and wheelchair fencing.

Carioca Arena 1 and the Olympic hockey centre are 100 percent complete and have already staged successful test events.

  

Top Stories


Leave a Comment

Title: Rio Olympic Park hits 97 percent completion



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.